Planned, Expected and Actual

From ReliaWiki
Jump to navigation Jump to search
This is a subpage of a larger section.
Return to: DFR Planner





Planned, Feasible and Actual

  • Planned dates and data hold the original dates and data (start end, duration, cost etc.) put in the planner.
  • Actual dates and data hold the final actual dates and data as recorded by the team on task/action/gate start/completion.
  • Feasible dates and data are automatically and continuously updated based on how the project progresses.
    • Feasible Start Date is the earliest possible date the gate or action can start (based on prior dependencies).
      • If there is no precedence or dependencies this is equal to the planned start date.
      • If there is a precedence then this is the earliest start date possible, after the completion of the precedence.
    • Feasible End Date is the expected completion date.
      • This is the "Feasible Start Date + Planned Duration".
    • Feasible Window is the length (in days) of the available time window to complete the action/gate.

In the ideal scenario, where each item is completed on-time and exactly as planned, all three are the same. In the real world however this is rarely the case.



Example

Consider the project shown in the table below comprised of three top level gates, six sub-gates and 12 actions.


DFR Example      
  G1: Gate 1    
    SG1: SubGate 1  
      Action 1000
      Action 1001
    SG2: SubGate 2  
      Action 1002
      Action 1003
  G2: Gate 2    
    SG3: SubGate 3  
      Action 1004
      Action 1005
    SG4: SubGate 4  
      Action 1006
      Action 1007
  G3: Gate 3    
    SG5: SubGate 5  
      Action 1008
      Action 1009
    SG6: SubGate 6  
      Action 1010
      Action 1011



Planning Stage

Settings and Assumptions

  • There is a same level precedence for each Gate and Sub-gate. No precedence is set for the actions within a gate, however the plans calls for them to run sequentially.
  • Monday, Tuesday, Wednesday, Thursday and Friday are workdays. Weekends include Saturday and Sunday. Holidays include December 25th, July 4th, January 1st, the fourth Thursday of November, the first Monday of September, and the last Monday of May. This is set through the Work Days Scheduler interface, which can be found in Manage Repository under the Repository Settings.
  • Each Action has a duration of three days.
  • Actions start at the beginning of the workday assigned (i.e. first thing in the morning)  and end at the end of the workday assigned.  For example a two day action starting on January 1 would be completed on January 2 (e.g. all day on day 1 and all day on day 2).
  • Action 1 starts in January 2, when completed Action 2 starts and so forth.
  • No lag time between gates and actions.

Planned Dates

Based on the above settings and assumptions, including weekends and holidays, the planned dates would be as follows:


DFR Plan
        Planned Dates
        Start Date Duration End Date
P1: Project 1       Jan-02 50 Feb-20
  G1: Gate 1     Jan-02 16 Jan-17
    SG1: SubGate 1   Jan-02 8 Jan-09
      Action 1000 Jan-02 5 Jan-06
      Action 1001 Jan-07 3 Jan-09
    SG2: SubGate 2   Jan-10 6 Jan-15
      Action 1002 Jan-10 5 Jan-14
      Action 1003 Jan-15 3 Jan-17
  G2: Gate 2     Jan-20 16 Feb-4
    SG3: SubGate 3   Jan-20 8 Jan-27
      Action 1004 Jan-20 3 Jan-22
      Action 1005 Jan-23 5 Jan-27
    SG4: SubGate 4 Jan-28 8 Feb-04
      Action 1006 Jan-28 3 Jan-30
      Action 1007 Jan-31 5 Feb-04
  G3: Gate 3     Feb-05 16 Feb-20
    SG5: SubGate 5   Feb-05 8 Feb-12
      Action 1008 Feb-05 3 Feb-07
      Action 1009 Feb-10 3 Feb-12
    SG6: SubGate 6   Feb-13 8 Feb-20
      Action 1010 Jan-31 5 Feb-02
      Action 1011 Feb-18 3 Feb-20

Planned Costs

Planned costs can be automatically included/calculated based on the resources assigned to each action. See also DFR Resources, which can be found in Manage Repository under the Repository Settings.

For this example we will only consider labor costs and ignore other cost variables.  From a labor prespective assume the following resources are assigned to the project.

Team Members & Resources For Project
Position Name Hrs/Day Cost Per Hour
Manager John Reliable 8 100
Manager Maria General 8 100
Employee 1 Employee 8 50
Employee 2 Employee 8 50
Employee 3 Employee 8 50
Employee 4 Employee 8 50


These are defined in team resources as follows:

Teams
Name Members
CUS Team 1 E1 & E2
CUS Team 2 E3 & E4
CUS All All


The allocation to tasks is as follows:


DFR Plan
        Planned Dates Manager Team
        Start Date Duration End Date Name % Allocation Name % Allocation
P1: Project 1       Jan-02 50 Feb-20
  G1: Gate 1     Jan-02 16 Jan-17
    SG1: SubGate 1   Jan-02 8 Jan-09
      Action 1000 Jan-02 5 Jan-06 John Reliable 25% CUS Team 1 100%
      Action 1001 Jan-07 3 Jan-09 Maria General 25% CUS ALL 80%
    SG2: SubGate 2   Jan-10 6 Jan-15
      Action 1002 Jan-10 5 Jan-14 John Reliable 50% CUS Team 2 100%
      Action 1003 Jan-15 3 Jan-17 Maria General 15% CUS ALL 100%
  G2: Gate 2     Jan-20 16 Feb-4
    SG3: SubGate 3   Jan-20 8 Jan-27
      Action 1004 Jan-20 3 Jan-22 John Reliable 50% CUS Team 2 100%
      Action 1005 Jan-23 5 Jan-27 Maria General 15% CUS Team 1 100%
    SG4: SubGate 4 Jan-28 8 Feb-04
      Action 1006 Jan-28 3 Jan-30 Maria General 20% CUS ALL 50%
      Action 1007 Jan-31 5 Feb-04 Maria General 70% CUS ALL 75%
  G3: Gate 3     Feb-05 16 Feb-20
    SG5: SubGate 5   Feb-05 8 Feb-12
      Action 1008 Feb-05 3 Feb-07 John Reliable 30% CUS Team 2 60%
      Action 1009 Feb-10 3 Feb-12 John Reliable 30% CUS Team 1 60%
    SG6: SubGate 6   Feb-13 8 Feb-20
      Action 1010 Jan-31 5 Feb-02 Maria General 50% CUS Team 1 80%
      Action 1011 Feb-18 3 Feb-20 Maria General 80% CUS ALL 100%



From the inputs as defined above then the planned costs would be:

DFR Plan
        Planned Dates Planned
        Start Date Duration End Date Cost
DFR Example       Jan-02 50 Feb-20 $146,040
  G1: Gate 1     Jan-02 16 Jan-17 $48,030
    SG1: SubGate 1   Jan-02 8 Jan-09 $30,660
      Action 1000 Jan-02 5 Jan-06 $7,650
      Action 1001 Jan-07 3 Jan-09 $23,010
    SG2: SubGate 2   Jan-10 6 Jan-15 $17,370
      Action 1002 Jan-10 5 Jan-14 $9,900
      Action 1003 Jan-15 3 Jan-17 $7,470
  G2: Gate 2     Jan-20 16 Feb-4 $50,910
    SG3: SubGate 3   Jan-20 8 Jan-27 $14,040
      Action 1004 Jan-20 3 Jan-22 $9,900
      Action 1005 Jan-23 5 Jan-27 $4,140
    SG4: SubGate 4 Jan-28 8 Feb-04 $36,870
      Action 1006 Jan-28 3 Jan-30 $14,460
      Action 1007 Jan-31 5 Feb-04 $22,410
  G3: Gate 3     Feb-05 16 Feb-20 $47,100
    SG5: SubGate 5   Feb-05 8 Feb-12 $10,800
      Action 1008 Feb-05 3 Feb-07 $5,940
      Action 1009 Feb-10 3 Feb-12 $4,860
    SG6: SubGate 6   Feb-13 8 Feb-20 $36,300
      Action 1010 Jan-31 5 Feb-02 $6,660
      Action 1011 Feb-18 3 Feb-20 $29,640


Planned Resource Loading

In this example the only resource used was personnel. Based on the prior entries each team member's utilization is as follows. Note that, in this case, overallocation exists for the two managers since they also serve on the CUS Teams.

PlannedResourceLoadingScreenShot.png

Execution Stage

Action 1

Assume that the project got started a day late, i.e. the initiating action (A01) got started on Jan-3 instead of Jan 2.

Then on Jan-3 the DFR Plan would then transform as follows:


ActionLateStart.png



Resource Conflicts

The late start of Action 1000 causes a resource conflict as shown next. Planned and Feasible dates are shown in this display. John Reliable, Eugene Doubter, and Maria General must allocate more resources to complete the project on time.

Dfrex1 1.png


Action 2

Assume that action A01 was completed on Jan-05 and A02 started on Jan-07.  Then the entire plan would shift as follows:


        Planned Dates Feasible Dates Actual Dates Planned Estimated Actual
        Start Date Duration End Date Start Date End Date Start Date Duration End Date Cost Cost-to-Date Cost
P1: Project 1       Jan-01 36 Feb-05 Jan-01 Feb-08 Jan-02   $38,520.00) $5,480.00) $4,000.00)
  G1: Gate 1     Jan-01 12 Jan-12 Jan-01 Jan-15 Jan-02   $13,800.00) $5,480.00) $4,000.00)
    SG11: SubGate 11   Jan-01 6 Jan-06 Jan-01 Jan-09 Jan-02   $7,440.00) $5,480.00) $4,000.00)
      A01: Action 1 Jan-01 3 Jan-03 Jan-01 Jan-04 Jan-02 4 Jan-05 $3,000.00) $4,000.00) $4,000.00)
      A02: Action 2 Jan-04 3 Jan-06 Jan-04 Jan-09 Jan-07   $4,440.00) $1,480.00)
    SG12: SubGate 12   Jan-07 6 Jan-12 Jan-10 Jan-15   $6,360.00)
      A03: Action 3 Jan-07 3 Jan-09 Jan-10 Jan-12   $3,600.00)
      A04: Action 4 Jan-10 3 Jan-12 Jan-13 Jan-15   $2,760.00)
  G2: Gate 2     Jan-13 12 Jan-24 Jan-16 Jan-27   $13,680.00)
    SG21: SubGate 21   Jan-13 6 Jan-18 Jan-16 Jan-21   $5,520.00)
      A05: Action 5 Jan-13 3 Jan-15 Jan-16 Jan-18   $3,600.00)
      A06: Action 6 Jan-16 3 Jan-18 Jan-19 Jan-21   $1,920.00)
    SG22: SubGate 22 Jan-19 6 Jan-24 Jan-22 Jan-27   $8,160.00)
      A07: Action 7 Jan-19 3 Jan-21 Jan-22 Jan-24   $2,880.00)
      A08: Action 8 Jan-22 3 Jan-24 Jan-25 Jan-27   $5,280.00)
  G3: Gate 3     Jan-25 12 Feb-05 Jan-28 Feb-08   $11,040.00)
    SG31: SubGate 31   Jan-25 6 Jan-30 Jan-28 Feb-02   $4,560.00)
      A09: Action 9 Jan-25 3 Jan-27 Jan-28 Jan-30   $2,160.00)
      A10: Action 10 Jan-28 3 Jan-30 Jan-31 Feb-02   $2,400.00)
    SG32: SubGate 32   Jan-31 6 Feb-05 Feb-03 Feb-08   $6,480.00)
      A11: Action 11 Jan-31 3 Feb-02 Feb-03 Feb-05   $3,120.00)
      A12: Action 12 Feb-03 3 Feb-05 Feb-06 Feb-08   $3,360.00)

End Section

SynXBuild.gif


Basis, Impact & Discussion

Basis for Modification

Basis Discuss

Impact on V8/V9 Users

Impact Discuss

Discussion Comment on this feature, or discuss it in the Synthesis Discussion area of our Discussion Forums.

These pages are not intended to replace, or be used in-lieu of the official software documentation. They are working/developments notes intended to facilitate communication between the user community and the development team. Features and specifications listed here are for discussion purposes and their final implementation in may be different than the specifications presented here.