Planned, Expected and Actual

From ReliaWiki
Revision as of 15:40, 24 July 2014 by Pantelis (talk | contribs)
Jump to navigation Jump to search
This is a subpage of a larger section.
Return to: DFR Planner





Planned, Feasible and Actual

  • Planned dates and data hold the original dates and data (start end, duration, cost etc.) put in the planner.
  • Actual dates and data hold the final actual dates and data as recorded by the team on task/action/gate start/completion.
  • Feasible dates and data are automatically and continuously updated based on how the project progresses.
    • Feasible Start Date is the earliest possible date the gate or action can start (based on prior dependencies). If there is no precedence or dependencies this is equal to the planned start date.
    • Feasible End Date is the expected completion date.
    • Feasible Duration is the length (in days) of the available time window to complete the action/gate.

In the ideal scenario, where each item is completed on-time and exactly as planned, all three are the same. In the real world however this is rarely the case.


End Section

SynXBuild.gif


Basis, Impact & Discussion

Basis for Modification

Basis Discuss

Impact on V8/V9 Users

Impact Discuss

Discussion Comment on this feature, or discuss it in the Synthesis Discussion area of our Discussion Forums.

These pages are not intended to replace, or be used in-lieu of the official software documentation. They are working/developments notes intended to facilitate communication between the user community and the development team. Features and specifications listed here are for discussion purposes and their final implementation in may be different than the specifications presented here.