==== Description ====
==== Description ====


Three devices A, B and C are in parallel. 2 out of 3 are required to perform the task. Initially A and B are working, C is in standby status.
Three devices A, B and C are in parallel. 2 out of 3 are required to perform the task. Initially A and B are working, C is in standby status. If A or B fails, C will replace
the failed one with some delay. After the failed device is restored, it will become a standby device. For example, If A fails, with 10 hours delay C will become active and replace A. After A is restored, it will become a standby device for B and C.

Revision as of 18:19, 10 August 2011

SCT with delay

Purposes

The purposes of this example is to illustrate how to apply SCT with delay.

Description

Three devices A, B and C are in parallel. 2 out of 3 are required to perform the task. Initially A and B are working, C is in standby status. If A or B fails, C will replace the failed one with some delay. After the failed device is restored, it will become a standby device. For example, If A fails, with 10 hours delay C will become active and replace A. After A is restored, it will become a standby device for B and C.