In ReliaSoft RBI and API 581 risk is equal to the product of the probability of failure and the consequence of failure.


=Calculation of Risk=
In ReliaSoft RBI and API 581 risk is equal to the product of the probability of failure and the consequence of failure. This can be seen in the below graphic.


[[File:RiskCalc.PNG]]
=Risk Cannot be Zero=
Risk cannot ever be equal to zero because residual risk factors always exist. The below graphic shows how residual risk is not affected by RBI.
Risk cannot ever be equal to zero because residual risk factors always exist. The below graphic shows how residual risk is not affected by RBI.




[[File:Risk vs. Level of Inspection.PNG]]
[[File:Risk vs. Level of Inspection.PNG]]

Revision as of 17:30, 22 April 2014



Calculation of Risk

In ReliaSoft RBI and API 581 risk is equal to the product of the probability of failure and the consequence of failure. This can be seen in the below graphic.

RiskCalc.PNG

Risk Cannot be Zero

Risk cannot ever be equal to zero because residual risk factors always exist. The below graphic shows how residual risk is not affected by RBI.