BlockSim Example: CM Triggered by Subsystem Down: Difference between revisions

From ReliaWiki
Jump to navigation Jump to search
 
(35 intermediate revisions by 3 users not shown)
Line 1: Line 1:
== CM Triggered by Subsystem Down ==
<noinclude>{{Banner BlockSim Examples}}{{Navigation box}}
 
</noinclude>
=== Purposes ===
This example illustrates how to model the case when corrective maintenance is triggered by the failure of a subsystem. We present two methods: one without a subdiagram and one with a subdiagram. The limitation of the method without a subdiagram is that it cannot model a subsystem with more than two devices in parallel or a more complex structure.  The method with a subdiagram is free of this limitation.
 
The purpose of this example is to illustrate how to model the case when CM is triggered by failure of subsystem. We present two kinds of methods: method without subdiagram and method with subdiagram. The limitation of the method without subdaigram is that, it cannot model subsystem with more than two devices in parallel or more complex structure.  The method with subdiagram can break this limitation.


=== Method 1: Without subdiagram ===
=== Method 1: Without subdiagram ===


Let’s consider a system with three devices A, B and C are in parallel. A and B form a subsystem AB. Only both A and B fail (subsystem AB fails), then start to repair A and B. Device C is parallel with subsystem AB. The repair of C depends on its failure. When C fails, then start to repair C.
Consider a system with three devices, A, B and C, in parallel. A and B form a subsystem, AB. If both A and B fail (i.e., if subsystem AB fails), then start to repair A and B. Device C is in parallel with subsystem AB. The repair of C depends on its failure. When C fails, then start to repair C.


==== BlockSim Solution ====
==== BlockSim Solution ====


The BlockSim modeling of this system is shown in Figure below.  
The BlockSim modeling of this system is shown in the figure below.  


[[Image:System_CM_triggered_by_subsystem_down.png‎|thumb|center|500px]]
[[Image:System_CM_triggered_by_subsystem_down.png‎|center|500px]]


Reliability of all blocks follow Weibull distribution with Beta =1.5 and Eta=500 hours.
*The reliability of all blocks follows a Weibull distribution with Beta = 1.5 and Eta = 500 hours.
*Block A and Block B belong to maintenance group MG_AB.
*The corrective maintenance of Block A and Block B are set to "When found failed during an inspection." The corrective maintenance duration is 120 hours. Upon repair, they are as good as new.
*An inspection is set up for both Blocks A and B. The inspection is performed based on events in maintenance group MG_AB. If any of the blocks in the maintenance group fail or if corrective maintenance starts for any of them, then the inspection is performed. The inspection duration is set to "Immediate Repair" and upon inspection; the device is restored to same as it was when it failed (i.e., as bad as old).
*The corrective maintenance of Block C is performed upon failure of Block C and the duration is 20 hours. It is as good as new upon repair.


Block A and Block B are belonging to maintenance group MG_AB.
==== Block Up/Down plot  ====


CM of Block A and B are set to "When found failed during an inspection". The CM duration is 120 hour. Upon repair, they are as good as new.
The system event log is shown in the figure below and explained next:


There is an inspection for both block A and B. The inspection is performed based on events in maintenance group MG_AB. If "Block fails" or "Start of corrective maintenance" event occurs for any of the blocks in the maintenance group MG_AB, then the inspection is performed. The inspection duration is set to "Immediate Repair" and upon inspection; the device is restored to same as it was when it failed (as bad as old).
#At 271 hours, Block C fails and the repair is finished at 291 hours.
#At 331 hours, Block B fails. Since the subsystem AB is not down (if both A and B fails, then subsystem AB fails), Block B is waiting for repair. (The failure of Block B cannot trigger an inspection of Block B, but this failure would trigger the inspection of Block A. However, Block A has not failed at this time, thus nothing happens).  
#At 381 hours, Block A fails and subsystem AB fails. The failure of the subsystem triggers the inspection and then inspection triggers corrective maintenance. (The failure of Block A triggers an inspection on Block B, which is currently failied. Thus corrective maintenance of Block B is performed. Performing corrective maintenance on Block B triggers the inspection of Block A. Since Block A is also currently failed, thus corrective maintenance of Block A is performed too.)
#At 501 hours, both Block A and B are restored.  
#At 791 hours, Block B fails and is waiting for repair.
#At 943 hours, Block C fails and is restored at 963 hours.
#At 1358 hours, Block A fails and subsystem AB fails, triggering corrective maintenance for Block A and B.
#At 1478 hours, both Block A and B are restored.
#...


CM of Block C is performed upon failure of Block C and the duration is 20 hours. It is as good as new upon repair.
<br> [[Image:CM triggered by susbystem failure Up Down plot.png|center|600px]]


==== Block Up/Down plot ====
=== Method 2: With subdiagram ===
Now consider a system consisting of four devices A, B, C and D. Devices A, B and C are in a parallel structure and form a subsystem, ABC. If all of A, B and C fail (i.e, if subsystem ABC fails), then start to repair devices A, B and C. Device D is parallel with subsystem ABC. The repair of D depends on its failure. When D fails, then start to repair D. Method 1 cannot model this system. Here we use a subdiagram to model the subsystem.


The system event log is shown in Figure belwo and is as follows:
==== BlockSim Solution  ====
The BlockSim model of this system is shown in the figure below.


#At 271, Block C fails and get repair at 291.
[[Image:CM_triggered_by_subsystem_down_(subdiagram_solution)_Main.png|center|500px]]
#At 331, Block B fails. Since the subsystem AB is not down (Both A and B fails, then subsystem AB fails), Block B is waiting for repair opportunity after its failure. (Failure of Block B cannot trigger inspection of Block B, but this failure would trigger the inspection of Block A. However, Block A doesn't have failure at this time, thus nothing happens).  
#At 381, Block A fails and subsystem AB fails. Subsystem fails trigger the inspection and then inspection triggers CM. (failure of Block A triggers an inspection on Block B, and Block B has failure at this point. Thus CM of Block B is performed. Performing CM on Block B triggers the inspection of Block A and Block A also has failure at this time, thus CM of Block A is performed too.)
#At 501, both Block A and B are restored.
#At 791, Block B fails and is waiting for repair opportunity.
#At 943, Block C fails and get restored at 963.
#At 1358, Block A fails and subsystem AB fails, triggering CM for Block A and B.
#At 1478, both Block A and B are restored.
#...


<br> [[Image:CM triggered by susbystem failure Up Down plot.png|thumb|center|500px]]
By using a subdiagram, we can break the limitation in method 1.


=== Method 2: With subdiagram ===
*The reliability of all blocks follows a Weibull distribution with Beta = 1.5 and Eta = 100 hours.
Let’s a system consists of four devices A, B, C and D. Devices A, B and C are in parallel structure and form a subsystem ABC. Only all A, B and C fail (subsystem ABC fails), then start to repair devices A, B and C. Device D is parallel with subsystem ABC. The repair of D depends on its failure. When D fails, then start to repair D. Method 1 cannot model this system. Here we use subdiagram to model the subsystem.
*The subdiagram block ABC belongs to maintenance group MG_ABC.
*The corrective maintenance of Blocks A, B and C are set to "When found failed during an inspection." The corrective maintenance duration is 20 hours. Upon repair, they are as good as new.
*An inspection is set up for Blocks A, B and C. The inspection is performed based on events in maintenance group MG_ABC. If any of the blocks in the maintenance group fail or if corrective maintenance starts for any of them, then the inspection is performed. The inspection duration is 30 hours. Upon inspection, the device is restored to the same condition it was in prior to the inspection (i.e., as bad as old).
*The corrective maintenance of Block D is performed upon the failure of Block D and the duration is 40 hours. It is as good as new upon repair.


==== BlockSim Solution ====
==== &nbsp;Block Up/Down plot ====
The BlockSim model of this system is shown in the Figure 5 below. By using subdiagram, we can break the limitation in method 1.


Reliability of all blocks follow Weibull distribution with Beta = 1.5 and Eta = 100 hours.
The system event log is shown in the figure below and explained next:
Subdiagram block ABC belongs to maintenance group MG_ABC.
CM of Block A, B and C are set to "When found failed during an inspection". The CM duration is 20 hour. Upon repair, they are as good as new.
There is an inspection for Block A, B and C. The inspection is performed based on events in maintenance group MG_ABC. If "Block fails" event occurs for any of the blocks in the maintenance group MG_ABC, then the inspection is performed. The inspection duration is 30 hours. Upon inspection, the device is restored to as bad as old.
CM of Block D is performed upon failure of Block C and the duration is 40 hours. It is as good as new upon repair.


[[Image:CM_triggered_by_subsystem_down_(subdiagram_solution)_Main.png|thumb|center|500px]]
#At 13 hours, Block C fails. Since subsystem ABC doesn't fail, Block C waits for repair.
#At 111 hours, Block B fails. Since subsystem ABC doesn't fail, Block B waits for repair.
#At 176 hours, Block A fails and brings down the subsystem ABC. The failure of subsystem ABC triggers the inspection of Blocks A, B and C.
#At 197 hours, Block D fails and is repaired at 237 hours.
#At 206 hours, inspection on Blocks A, B and C is complete. It triggers corrective maintenance on all three blocks.
#At 226 hours, Blocks A, B and C are restored.
#...


[[Category:BlockSim_Examples]]
<br> [[Image:CM triggered by subsystem down (subdiagram solution) Up Down plot.png|center|600px]]

Latest revision as of 07:26, 6 August 2012

BlockSim Examples Banner.png


New format available! This reference is now available in a new format that offers faster page load, improved display for calculations and images and more targeted search.

As of January 2024, this Reliawiki page will not continue to be updated. Please update all links and bookmarks to the latest references at BlockSim examples and BlockSim reference examples.





This example illustrates how to model the case when corrective maintenance is triggered by the failure of a subsystem. We present two methods: one without a subdiagram and one with a subdiagram. The limitation of the method without a subdiagram is that it cannot model a subsystem with more than two devices in parallel or a more complex structure. The method with a subdiagram is free of this limitation.

Method 1: Without subdiagram

Consider a system with three devices, A, B and C, in parallel. A and B form a subsystem, AB. If both A and B fail (i.e., if subsystem AB fails), then start to repair A and B. Device C is in parallel with subsystem AB. The repair of C depends on its failure. When C fails, then start to repair C.

BlockSim Solution

The BlockSim modeling of this system is shown in the figure below.

System CM triggered by subsystem down.png
  • The reliability of all blocks follows a Weibull distribution with Beta = 1.5 and Eta = 500 hours.
  • Block A and Block B belong to maintenance group MG_AB.
  • The corrective maintenance of Block A and Block B are set to "When found failed during an inspection." The corrective maintenance duration is 120 hours. Upon repair, they are as good as new.
  • An inspection is set up for both Blocks A and B. The inspection is performed based on events in maintenance group MG_AB. If any of the blocks in the maintenance group fail or if corrective maintenance starts for any of them, then the inspection is performed. The inspection duration is set to "Immediate Repair" and upon inspection; the device is restored to same as it was when it failed (i.e., as bad as old).
  • The corrective maintenance of Block C is performed upon failure of Block C and the duration is 20 hours. It is as good as new upon repair.

Block Up/Down plot

The system event log is shown in the figure below and explained next:

  1. At 271 hours, Block C fails and the repair is finished at 291 hours.
  2. At 331 hours, Block B fails. Since the subsystem AB is not down (if both A and B fails, then subsystem AB fails), Block B is waiting for repair. (The failure of Block B cannot trigger an inspection of Block B, but this failure would trigger the inspection of Block A. However, Block A has not failed at this time, thus nothing happens).
  3. At 381 hours, Block A fails and subsystem AB fails. The failure of the subsystem triggers the inspection and then inspection triggers corrective maintenance. (The failure of Block A triggers an inspection on Block B, which is currently failied. Thus corrective maintenance of Block B is performed. Performing corrective maintenance on Block B triggers the inspection of Block A. Since Block A is also currently failed, thus corrective maintenance of Block A is performed too.)
  4. At 501 hours, both Block A and B are restored.
  5. At 791 hours, Block B fails and is waiting for repair.
  6. At 943 hours, Block C fails and is restored at 963 hours.
  7. At 1358 hours, Block A fails and subsystem AB fails, triggering corrective maintenance for Block A and B.
  8. At 1478 hours, both Block A and B are restored.
  9. ...


CM triggered by susbystem failure Up Down plot.png

Method 2: With subdiagram

Now consider a system consisting of four devices A, B, C and D. Devices A, B and C are in a parallel structure and form a subsystem, ABC. If all of A, B and C fail (i.e, if subsystem ABC fails), then start to repair devices A, B and C. Device D is parallel with subsystem ABC. The repair of D depends on its failure. When D fails, then start to repair D. Method 1 cannot model this system. Here we use a subdiagram to model the subsystem.

BlockSim Solution

The BlockSim model of this system is shown in the figure below.

CM triggered by subsystem down (subdiagram solution) Main.png

By using a subdiagram, we can break the limitation in method 1.

  • The reliability of all blocks follows a Weibull distribution with Beta = 1.5 and Eta = 100 hours.
  • The subdiagram block ABC belongs to maintenance group MG_ABC.
  • The corrective maintenance of Blocks A, B and C are set to "When found failed during an inspection." The corrective maintenance duration is 20 hours. Upon repair, they are as good as new.
  • An inspection is set up for Blocks A, B and C. The inspection is performed based on events in maintenance group MG_ABC. If any of the blocks in the maintenance group fail or if corrective maintenance starts for any of them, then the inspection is performed. The inspection duration is 30 hours. Upon inspection, the device is restored to the same condition it was in prior to the inspection (i.e., as bad as old).
  • The corrective maintenance of Block D is performed upon the failure of Block D and the duration is 40 hours. It is as good as new upon repair.

 Block Up/Down plot

The system event log is shown in the figure below and explained next:

  1. At 13 hours, Block C fails. Since subsystem ABC doesn't fail, Block C waits for repair.
  2. At 111 hours, Block B fails. Since subsystem ABC doesn't fail, Block B waits for repair.
  3. At 176 hours, Block A fails and brings down the subsystem ABC. The failure of subsystem ABC triggers the inspection of Blocks A, B and C.
  4. At 197 hours, Block D fails and is repaired at 237 hours.
  5. At 206 hours, inspection on Blocks A, B and C is complete. It triggers corrective maintenance on all three blocks.
  6. At 226 hours, Blocks A, B and C are restored.
  7. ...


CM triggered by subsystem down (subdiagram solution) Up Down plot.png