Duane Model
Duane
Model History and Development
In 1962, J. T. Duane published a report in which he presented failure data of different systems during their development programs [8]. While analyzing the data, it was observed that the cumulative MTBF versus cumulative operating time followed a straight line when plotted on log-log paper (Figure oldpic71).
Based on that observation, Duane developed his model as follows. If
The equation of the line can be expressed as:
Setting:
yields:
Then equating
or:
And, if you assume a constant failure intensity, then the cumulative failure intensity,
or:
Also, the expected number of failures up to time
where:
The corresponding
where
Similarly, using Eqn. (duanecnew), this procedure yields:
where
Parameter Estimation
The Duane model is a two parameter model. Therefore, to use this model as a basis for predicting the reliability growth that could be expected in an equipment development program, procedures must be defined for estimating these parameters as a function of equipment characteristics. Note that, while these parameters can be estimated for a given data set using curve-fitting methods, there exists no underlying theory for the Duane model that could provide a basis for a priori estimation.
Graphical Method
Eqn. (duaneb) may be linearized by taking the natural log of both sides:
Consequently, plotting
Similarly, Eqn. (duane6) can also be linearized by taking the natural log of both sides:
Plotting
Two ways of determining these curves are as follows:
- Predict the
and of the system from its reliability block diagram and available component failure intensities. Plot this value on log-log plotting paper at From past experience and from past data for similar equipment, find values of , the slope of the improvement lines for or . Modify this as necessary. If a better design effort is expected and a more intensive research, test and development or TAAF program is to be implemented, then a improvement in the growth rate may be attainable. Consequently, the available value for slope , and , should be adjusted by this amount. The value to be used will then be A line is then drawn through point and with the just determined slope , keeping in mind that is negative for the curve. This line should be extended to the design, development and test time scheduled to be expended to see if the failure intensity goal will indeed be achieved on schedule. It is also possible to find that the design, development and test time to achieve the goal may be earlier than the delivery date or later. If earlier, then either the reliability program effort can be judiciously and appropriately trimmed; or if it is an incentive contract, full advantage is taken of the fact that the failure intensity goal can be exceeded with the associated increased profits to the company. A similar approach may be used for the MTBF growth model, where is plotted at , and a line is drawn through the point and with slope to obtain the MTBF growth line. If values are not available, consult Table 4.1, which gives actual values for various types of equipment. These have been obtained from the literature or by MTBF growth tests. It may be seen from Table 4.1 that values range between 0.24 and 0.65. The lower values reflect slow early growth and the higher values reflect fast early growth.
Equipment | Slope( | |
---|---|---|
Computer system | Actual | 0.24 |
Easy to find failures were eliminated | 0.26 | |
All known failure causes were eliminated | 0.36 | |
Mainframe computer | 0.50 | |
Aerospace electronics | All malfunctions | 0.57 |
Relevant failures only | 0.65 | |
Attack radar | 0.60 | |
Rocket engine | 0.46 | |
Afterburning turbojet | 0.35 | |
Complex hydromechanical system | 0.60 | |
Aircraft generator | 0.38 | |
Modern dry turbojet | 0.48 |
1) During the design, development and test phase and at specific milestones, the
Example 1
A complex system's reliability growth is being monitored and the data set is given in Table 4.2.
Do the following:
1) Plot the cumulative MTBF growth curve.
2) Write the equation of this growth curve.
3) Write the equation of the instantaneous MTBF growth model.
4) Plot the instantaneous MTBF growth curve.
Point Number | Cumulative Test Time(hr) | Cumulative Failures | Cumulative MTBF(hr) | Instantaneous MTBF(hr) |
---|---|---|---|---|
1 | 200 | 2 | 100.0 | 100 |
2 | 400 | 3 | 133.0 | 200 |
3 | 600 | 4 | 150.0 | 200 |
4 | 3,000 | 11 | 273.0 | 342.8 |
Solution
- 1) Given the data in the second and third columns of Table 4.2, the cumulative MTBF,
, values are calculated in the fourth column. The information in the second and fourth columns is then plotted. Figure figold72 shows the cumulative MTBF while Figure figold72a shows the instantaneous MTBF. It can be seen that a straight line represents the MTBF growth very well on log-log scales.
- 1) Given the data in the second and third columns of Table 4.2, the cumulative MTBF,
By changing the x-axis scaling, you are able to extend the line to
Another way of determining
Then substitute this
Using the plot in Figure figold72, at
Substituting the first set of values,
1. Substituting the second set of values,
Averaging these two
2. Now the equation for the cumulative MTBF growth curve is:
3. The equation for the instantaneous MTBF growth curve using Eqn. (eq76) is:
Eqn. (eq80) is plotted in Figures figold72a and figold72b. In Figure figold72b, you can see that a parallel shift upward of the cumulative MTBF,
Least Squares (Linear Regression)
The parameters can also be estimated using a mathematical approach. To do this, apply least squares analysis on Eqn. (eq73):
And for simplicity in the calculations, let:
Therefore, Eqn. (mc) becomes:
Assume that a set of data pairs
And where
Differentiating
and:
Set Eqns. (ls2) and (ls3) equal to zero:
and:
Solve the equations simultaneously:
and:
Now substituting back
where:
Example 2
Using the data from Table 4.2, estimate the parameters of the MTBF model using least squares.
Solution
From Table 4.2:
From Eqn. (Dalpha):
Also from Eqn. (Dbi):
Therefore, Eqn. (duane6) becomes:
The equation for the instantaneous MTBF growth curve using Eqn. (eq76) is:
Example 3
For the data given in columns 1 and 2 of Table 4.3, estimate the Duane parameters using least squares.
(1)Failure Number | (2)Failure Time(hr) | (3) |
(4) |
(5) |
(6) |
(7) |
---|---|---|---|---|---|---|
1 | 9.2 | 2.219 | 4.925 | 9.200 | 2.219 | 4.925 |
2 | 25 | 3.219 | 10.361 | 12.500 | 2.526 | 8.130 |
3 | 61.5 | 4.119 | 16.966 | 20.500 | 3.020 | 12.441 |
4 | 260 | 5.561 | 30.921 | 65.000 | 4.174 | 23.212 |
5 | 300 | 5.704 | 32.533 | 60.000 | 4.094 | 23.353 |
6 | 710 | 6.565 | 43.103 | 118.333 | 4.774 | 31.339 |
7 | 916 | 6.820 | 46.513 | 130.857 | 4.874 | 33.241 |
8 | 1010 | 6.918 | 47.855 | 126.250 | 4.838 | 33.470 |
9 | 1220 | 7.107 | 50.504 | 135.556 | 4.909 | 34.889 |
10 | 2530 | 7.836 | 61.402 | 253.000 | 5.533 | 43.359 |
11 | 3350 | 8.117 | 65.881 | 304.545 | 5.719 | 46.418 |
12 | 4200 | 8.343 | 69.603 | 350.000 | 5.858 | 48.872 |
13 | 4410 | 8.392 | 70.419 | 339.231 | 5.827 | 48.895 |
14 | 4990 | 8.515 | 72.508 | 356.429 | 5.876 | 50.036 |
15 | 5570 | 8.625 | 74.393 | 371.333 | 5.917 | 51.036 |
16 | 8310 | 9.025 | 81.455 | 519.375 | 6.253 | 56.431 |
17 | 8530 | 9.051 | 81.927 | 501.765 | 6.218 | 56.282 |
18 | 9200 | 9.127 | 83.301 | 511.111 | 6.237 | 56.921 |
19 | 10500 | 9.259 | 85.731 | 552.632 | 6.315 | 58.469 |
20 | 12100 | 9.401 | 88.378 | 605.000 | 6.405 | 60.215 |
21 | 13400 | 9.503 | 90.307 | 638.095 | 6.458 | 61.375 |
22 | 14600 | 9.589 | 91.945 | 663.636 | 6.498 | 62.305 |
23 | 22000 | 9.999 | 99.976 | 956.522 | 6.863 | 68.625 |
Solution
To estimate the parameters using least squares, the values in columns 3, 4, 5, 6 and 7 are calculated. The cumulative MTBF,
The estimator of
Therefore, Eqn. (duane6) becomes:
Using Eqn. (eq76), the equation for the instantaneous MTBF growth curve is:
Example 4
For the data given in the Table 4.4, estimate the Duane parameters using least squares.
Run Number | Failed Unit | Test Time 1 | Test Time 2 | Cumulative Time |
---|---|---|---|---|
1 | 1 | 0.2 | 2.0 | 2.2 |
2 | 2 | 1.7 | 2.9 | 4.6 |
3 | 2 | 4.5 | 5.2 | 9.7 |
4 | 2 | 5.8 | 9.1 | 14.9 |
5 | 2 | 17.3 | 9.2 | 26.5 |
6 | 2 | 29.3 | 24.1 | 53.4 |
7 | 1 | 36.5 | 61.1 | 97.6 |
8 | 2 | 46.3 | 69.6 | 115.9 |
9 | 1 | 63.6 | 78.1 | 141.7 |
10 | 2 | 64.4 | 85.4 | 149.8 |
11 | 1 | 74.3 | 93.6 | 167.9 |
12 | 1 | 106.6 | 103 | 209.6 |
13 | 2 | 195.2 | 117 | 312.2 |
14 | 2 | 235.1 | 134.3 | 369.4 |
15 | 1 | 248.7 | 150.2 | 398.9 |
16 | 2 | 256.8 | 164.6 | 421.4 |
17 | 2 | 261.1 | 174.3 | 435.4 |
18 | 2 | 299.4 | 193.2 | 492.6 |
19 | 1 | 305.3 | 234.2 | 539.5 |
20 | 1 | 326.9 | 257.3 | 584.2 |
21 | 1 | 339.2 | 290.2 | 629.4 |
22 | 1 | 366.1 | 293.1 | 659.2 |
23 | 2 | 466.4 | 316.4 | 782.8 |
24 | 1 | 504 | 373.2 | 877.2 |
25 | 1 | 510 | 375.1 | 885.1 |
26 | 2 | 543.2 | 386.1 | 929.3 |
27 | 2 | 635.4 | 453.3 | 1088.7 |
28 | 1 | 641.2 | 485.8 | 1127 |
29 | 2 | 755.8 | 573.6 | 1329.4 |
Solution
The solution to this example follows the same procedure as the previous example. Therefore, from Table 4.4:
For least squares, Eqn. (Dalpha) is used to estimate
The estimator of
Therefore, from Eqn. (duane6):
Using Eqn. (eq76), the equation for the instantaneous MTBF growth curve is:
Maximum Likelihood Estimators
In Reliability Analysis for Complex, Repairable Systems (1974), L. H. Crow noted that the Duane model could be stochastically represented as a Weibull process, allowing for statistical procedures to be used in the application of this model in reliability growth. This statistical extension became what is known as the Crow-AMSAA (NHPP) model. The Crow-AMSAA provides a complete Maximum Likelihood Estimation (MLE) solution to the Duane model. This is described in detail in Chapter 5.
Confidence Bounds
Least squares confidence bounds can be computed for both the model parameters and metrics of interest for the Duane model.
Parameter Bounds
Apply least squares analysis on the Duane model:
The unbiased estimator of can be obtained from:
where:
Thus, the confidence bounds on
where
Other Bounds
Confidence bounds also can be obtained on the cumulative MTBF and the cumulative failure intensity:
When
and ; therefore, the confidence bounds on the instantaneous failure intensity are:
Example 5
For the data given in Table 4.3, calculate the 90% confidence bounds for:
- The parameters
. - The cumulative and instantaneous failure intensity.
- The cumulative and instantaneous MTBF.
Solution
1. Using the values of
Eqn. (duanec7) is:
Eqn. (duanec8) is:
Thus, 90% confidence bounds on parameter
And 90% confidence bounds on parameter
2. The cumulative failure intensity is:
And the instantaneous failure intensity is equal to:
So, at the 90% confidence level and for
For the instantaneous failure intensity:
Figures figure75 and figure76 show the graphs of the cumulative and instantaneous failure intensity. Both are plotted with confidence bounds.
3. The cumulative MTBF is:
And the instantaneous MTBF is:
So, at 90% confidence level and for
The confidence bounds for the instantaneous MTBF are:
Figure CumMTBFCB displays the cumulative MTBF while Figure InstMTBFCB displays the instantaneous MTBF. Both are plotted with confidence bounds.
General Examples
Example 6
A prototype of a system was tested with design changes incorporated during the test. A total of 12 failures occurred. The data set is given in Table 4.5.
- Estimate the Duane parameters.
- Plot the cumulative and instantaneous MTBF curves.
- How many cumulative test and development hours are required to meet an instantaneous MTBF goal #of 500 hours?
- How many cumulative test and development hours are required to meet a cumulative MTBF goal of 500 hours?
Failure Number | Cumulative Test Time(hr) |
---|---|
1 | 80 |
2 | 175 |
3 | 265 |
4 | 400 |
5 | 590 |
6 | 1100 |
7 | 1650 |
8 | 2010 |
9 | 2400 |
10 | 3380 |
11 | 5100 |
12 | 6400 |
Solution to Example 6
- Figure figuaneex11 shows the data entered into RGA along with the estimated Duane parameters.
- Figure figuaneex12 shows the cumulative and instantaneous MTBF curves.
- Figure figuaneex14 shows the cumulative test and development hours needed for an instantaneous MTBF goal of 500 hours.
- Figure figuaneex15 shows the cumulative test and development hours needed for a cumulative MTBF goal of 500 hours.
Example 7
Two identical systems were tested. Any design changes made to improve the reliability of these systems were incorporated into both systems when any system failed. A total of 29 failures occurred. The data set is given in Table 4.6. Do the following:
- Estimate the Duane parameters.
- Assume both units are tested for an additional 100 hrs each. How many failures do you expect in that period?
- If testing/development were halted at this point, what would the reliability equation for this system be?
Failure Number | Failed Unit | Test Time Unit 1(hr) | Test Time Unit 2 (hr) |
---|---|---|---|
1 | 1 | 0.2 | 2.0 |
2 | 2 | 1.7 | 2.9 |
3 | 2 | 4.5 | 5.2 |
4 | 2 | 5.8 | 9.1 |
5 | 2 | 17.3 | 9.2 |
6 | 2 | 29.3 | 24.1 |
7 | 1 | 36.5 | 61.1 |
8 | 2 | 46.3 | 69.6 |
9 | 1 | 63.6 | 78.1 |
10 | 2 | 64.4 | 85.4 |
11 | 1 | 74.3 | 93.6 |
12 | 1 | 106.6 | 103 |
13 | 2 | 195.2 | 117 |
14 | 2 | 235.1 | 134.3 |
15 | 1 | 248.7 | 150.2 |
16 | 2 | 256.8 | 164.6 |
17 | 2 | 261.1 | 174.3 |
18 | 2 | 299.4 | 193.2 |
19 | 1 | 305.3 | 234.2 |
20 | 1 | 326.9 | 257.3 |
21 | 1 | 339.2 | 290.2 |
22 | 1 | 366.1 | 293.1 |
23 | 2 | 466.4 | 316.4 |
24 | 1 | 504 | 373.2 |
25 | 1 | 510 | 375.1 |
26 | 2 | 543.2 | 386.1 |
27 | 2 | 635.4 | 453.3 |
28 | 1 | 641.2 | 485.8 |
29 | 2 | 755.8 | 573.6 |
Solution to Example 7
1) Figure figuaneex21 shows the data entered into RGA along with the estimated Duane parameters.
2) The current accumulated test time for both units is 1329.4 hr. If the process were to continue for an additional combined time of 200 hr, the expected cumulative number of failures at
3) If testing/development were halted at this point, the system failure intensity would be equal to the instantaneous failure intensity at that time, or
Weibull++ can be utilized (from within RGA) to provide a Reliability vs. Time plot. This is shown in Figure figuaneex24.
Example 8
Given the sequential success/failure data in the Table 4.7, do the following:
1) Estimate the Duane parameters.
2) What is the instantaneous MTBF at the end of the test?
3) How many additional test runs with a one-sided 90% confidence level are required to meet an instantaneous MTBF goal of 5 hours?
Run Number | Result |
---|---|
1 | F |
2 | F |
3 | S |
4 | S |
5 | S |
6 | F |
7 | S |
8 | F |
9 | F |
10 | S |
11 | S |
12 | S |
13 | F |
14 | S |
15 | S |
16 | S |
17 | S |
18 | S |
19 | S |
20 | S |
Solution to Example 8
1) Figure figuaneex31 shows the data set entered into RGA along with the estimated Duane parameters.
2) The MTBF at the end of the test is equal to 4.5904 hours. Note that this is the DMTBF that is shown in the Control Panel in Figure figuaneex31.
3) Figure figuaneex34 shows the number of test runs with both one-sided confidence bounds at 90% confidence level to achieve an instantaneous MTBF of 5 hours. Therefore, the number of additional test runs required with a 90% confidence level is equal to