== Phase with F/S links ==
#REDIRECT [[Example_Using_Success_Failure_Paths_in_Phase_Diagrams]]
 
==== Purposes ====
 
The purposes of this example is to illustrate how to apply F/S links in Phase simulation.
 
==== RBDs for Phase and settings ====
The RBDs for Phase 1 and Phase 2 are as followings:
[[Image:RBD_for_Phase_1_and_2.png|thumb|center|500px]]
 
In Phase 1, Block A follows Weibull distribution with Beta = 1.5 and Eta = 1000 hours. Block B follows Weibull distribution with Beta = 1.5 and Eta = 1200 hours. No maintenance.
 
In Phase 2, Block A follows Weibull distribution with Beta = 1.5 and Eta = 900 hours. Block B follows Weibull distribution with Beta = 1.5 and Eta = 1150 hours. No maintenance.
 
==== Example 1 ====
The Phase diagram is as followings:
[[Image:Phase_Example_1.png‎|thumb|center|500px]]
 
Maintenance phase has a CM with duration 80 hours and PM with duration 20 hours for both Block A and B.
 
Phase 1 has duration 500 hours and Phase 2 has duration 100 hours.
 
If there is no failure in Phase 1, upon finish, it goes to Phase 2. If there is a failure in Phase 1, it would go to Maintenance Phase 3 directly. If there is not failure in Phase 2, upon finish, it goes back to Phase 1. If there is a failure in Phase 2, it would to go Maintenance Phase 3.
 